Weighted Progress %

Overall % complete from activity weights, compared with the plan

Design data
%
%
%
%
%
%
%
%
%
ResultPreliminary · verify before design
Overall progress40.0 %Planned 50.0 % · SPI 0.80
Over limitWell behind plan: recovery programme needed
Weights total100.0 %
Earned weight40.0 %
Progress variance (actual − planned)-10.0 %
Schedule performance index (SPI)0.80

Weights usually come from the budget (cost-loaded) or man-hours of each activity, fixed in the approved baseline. % complete follows the agreed rules of credit (for example 10 % on delivery, 60 % installed, 30 % tested).

What to verify before design ↓

Verify before using in design

  • Weights and rules of credit match the approved baseline and the progress measurement procedure.
  • Planned % at the data date taken from the approved S-curve, not a straight line.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by a senior engineer · Nov 2026

Formula

Progress = Σ(weight × % complete) ÷ Σ weights SPI = actual % ÷ planned %

Standards and references

  • Project baseline: activity weights and rules of credit
  • AACE International recommended practices on progress measurement
  • PMI Practice Standard for Scheduling

Assumptions

  • Weights fixed in the baseline; % complete per activity measured by the agreed rules of credit; % above 100 counted as 100.

Inputs and units

Weight of activity 1%0–100
Activity 1 complete%0–100
Weight of activity 2%0–100
Activity 2 complete%0–100
Weight of activity 3%0–100
Activity 3 complete%0–100
Weight of activity 4 (0 if none)%0–100
Activity 4 complete%0–100
Planned % complete at the data date%1–100

Typical range: last column

Worked example (default values)

  • Weight of activity 115 %
  • Activity 1 complete100 %
  • Weight of activity 230 %
  • Activity 2 complete60 %
  • Weight of activity 335 %
  • Activity 3 complete20 %
  • Weight of activity 4 (0 if none)20 %
  • Activity 4 complete0 %
  • Planned % complete at the data date50 %
Overall progress40.0 %Well behind plan: recovery programme needed