Punch List Closure Forecast

Will the snags be closed by handover at the current rate?

Design data
ResultPreliminary · verify before design
Weeks to close all items7.6 weeks55 items a week net (85 closed − 30 new)
Over limitLate by about 1.6 weeks: close at least 100 items a week
Net reduction per week55 items
Closure rate needed to finish on time100 items/week
Items left at handover at today's rate90

A forecast from recent averages, not a promise. Category A items (those that block handover) deserve their own forecast: run it again with only those items.

What to verify before design ↓

Verify before using in design

  • Use rates from the last 3–4 weeks of the punch list, not a single good week.
  • Check re-inspection capacity: items 'ready for re-inspection' only count once the consultant closes them.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Oct 2026✓ Tested against worked examples

Formula

Weeks = open ÷ (closed per week − new per week) Needed = open ÷ weeks left + new per week

Standards and references

  • Project completion and handover procedure
  • Contract conditions for taking over (e.g. FIDIC 2017 Clause 10)

Assumptions

  • Closing and new-item rates stay at their recent average.
  • All items are treated alike; category A items can be forecast on their own.

Inputs and units

Items not closed today
Items closed per week (recent average)
New items raised per week
Weeks left to the handover date0.5–52

Typical range: last column

Worked example (default values)

  • Items not closed today420
  • Items closed per week (recent average)85
  • New items raised per week30
  • Weeks left to the handover date6
Weeks to close all items7.6 weeksLate by about 1.6 weeks: close at least 100 items a week