Practical Completion & Handover
Handover is where a project is judged. The client doesn't see the programme or the method statements; they see whether the building works, the snags are closed and the documents are there. Planning it from the middle of the job is what makes the last month calm.
The sequence
- Installation complete → testing and commissioning → snagging and de-snagging → handover documents → training → client inspection → taking-over certificate (practical completion).
- Big projects hand over in sections or systems; agree the sections and their dates in the contract or early in the job.
- Authority approvals (civil defence, electricity and water utility, municipality) often set the real critical path: book them early.
Snagging
- Do your own internal snagging first, before the consultant walks.
- Every item gets a number, location, photo, category and an owner. Category A items block handover; B and C items can follow within an agreed period.
- Close items with evidence and a re-inspection, not a phone call.
- Track the closure rate weekly; if new items arrive as fast as old ones close, add resources early.
Handover documents and training
- O&M manuals, as-built drawings, test and commissioning records, warranties, spare parts lists and keys, organised by system.
- An asset register with tags, makes, models and serial numbers, in the format the client's facilities team will use.
- Training sessions for the operators, recorded with attendance and the material handed over.
- A handover index shows what each system still needs; a system is ready only when everything is approved.