Retention Money & Release

Retention held, the limit, and what is released at taking-over

Design data
%
%
%
ResultPreliminary · verify before design
Retention held now2,500,000Limit reached (5.0 % of the contract sum)
Within limitLimit reached: no more retention is deducted from later payments
Released at taking-over1,250,000
Held until the end of the defects period1,250,000
Limit of retention money2,500,000
Limit is reached at certified value25,000,000

Typical FIDIC-style arrangement: retention is deducted from each interim payment up to a limit, half is released at taking-over and the rest after the defects notification period. Your contract sets the rate, limit, release stages and whether a retention bond can replace cash; amounts are in any one currency.

What to verify before design ↓

Verify before using in design

  • Check the contract data for rate, limit, release stages and sectional taking-over.
  • Retention on variations and price adjustments depends on the contract wording.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Oct 2026✓ Tested against worked examples

Formula

Held = min(certified × rate, contract sum × limit) Released at taking-over = held × share

Standards and references

  • FIDIC 2017 Red / Yellow Book Sub-Clauses 14.3 and 14.9 (retention money)
  • Particular conditions and contract data of your contract

Assumptions

  • Retention is a fixed percentage of each certified amount, up to a limit.
  • One release at taking-over and the balance after the defects period.

Inputs and units

Accepted contract sum
Value of work certified to date
Retention rate on each payment%1–10
Limit of retention money (% of contract sum)%1–10
Share released at taking-over%0–100

Typical range: last column

Worked example (default values)

  • Accepted contract sum50000000
  • Value of work certified to date32000000
  • Retention rate on each payment10 %
  • Limit of retention money (% of contract sum)5 %
  • Share released at taking-over50 %
Retention held now2,500,000Limit reached: no more retention is deducted from later payments