Unit Rate Build-up

Labour, material with wastage, plant, then overheads and profit

Design data
%
%
ResultPreliminary · verify before design
Unit rate205.45Direct cost 178.65 + 15.0 % OH&P
Within limitCompare with BOQ rates for similar work before using it as a star rate
Labour14.40 (8 %)
Material incl. wastage152.25 (85 %)
Plant12.00 (7 %)
Direct cost178.65
OH&P amount26.80

Amounts in any one currency. Labour rate should be all-in (wages, allowances, accommodation, transport, visas). Overheads and profit, and whether they apply to a variation, follow the contract. Use the build-up to check or justify a star rate, not to replace market quotations.

What to verify before design ↓

Verify before using in design

  • Check outputs (hours per unit) against your own records, not catalogues only.
  • Confirm whether the contract allows OH&P on the variation.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Oct 2026✓ Tested against worked examples

Formula

Rate = (labour hours × labour rate + material × (1 + wastage) + plant) × (1 + OH&P)

Standards and references

  • Contract valuation rules (e.g. FIDIC 2017 Sub-Clause 12.3 and Clause 13)
  • Company estimating procedure

Assumptions

  • One unit of work; labour, material and plant costs per that unit.
  • OH&P applied to the whole direct cost.

Inputs and units

Labour hours per unit
Labour cost per hour (all-in)
Material cost per unit (delivered)
Material wastage%0–30
Plant and equipment per unit
Overheads and profit (OH&P)%0–40

Typical range: last column

Worked example (default values)

  • Labour hours per unit0.8
  • Labour cost per hour (all-in)18
  • Material cost per unit (delivered)145
  • Material wastage5 %
  • Plant and equipment per unit12
  • Overheads and profit (OH&P)15 %
Unit rate205.45Compare with BOQ rates for similar work before using it as a star rate