Quantity Takeoff & Bills of Quantities
A bill of quantities turns drawings into priced items everyone can compare. Its value depends on two things: measuring to an agreed method, and keeping every quantity traceable to a drawing and a calculation.
Methods of measurement
- The contract names the method of measurement: commonly POMI (RICS Principles of Measurement International) in the Gulf, CESMM4 for civil works, or NRM2.
- The method decides units, what each item includes (working space, formwork, laps), and when deductions are made.
- Preambles and item descriptions must match the method; a mismatch is a common source of disputes.
Taking off
- Work from the latest drawings and note their revisions; measure systematically (by element, level and grid) so nothing is missed or double-counted.
- Use a dimension sheet: times × length × width × depth, with deductions for openings and voids.
- Keep the takeoff for every item; when drawings change, re-measure the affected parts rather than adjusting totals by eye.
- Rebar comes from bar bending schedules, MEP lengths from routed layouts including drops and bends.
Using the BOQ
- In a remeasurement contract the BOQ quantities are estimates and the work is measured as built; in a lump-sum contract the quantities may be at the contractor's risk.
- Interim payments are valued from measured progress against BOQ items.
- Provisional sums and prime cost sums cover work not yet designed or nominated supplies; they are adjusted when the work is defined.