Variations & Change Control

Almost every project changes after the contract is signed. Variations are normal; what goes wrong is the process: work done on a verbal instruction, notices sent late, or valuations nobody can trace.

Instruction and notice

  • Only the person authorised by the contract (under FIDIC, the Engineer) can instruct a variation; get it in writing before doing the work.
  • If something changes without an instruction, notify it promptly. Under FIDIC 2017 a claim notice is due within 28 days of becoming aware of the event; late notice can lose the entitlement.
  • Log every variation from the day it is identified, with the instruction, notice, quotation and agreement linked.

Valuation

  • Use contract rates where the work is similar and done in similar conditions; pro-rata rates where it is similar but conditions differ.
  • Where nothing is comparable, agree a star rate built up from labour, material and plant, or record the work as dayworks with daily signed sheets.
  • Omissions are valued at contract rates; check whether omitted work affects overheads.
  • Follow the contract's rules on OH&P, and keep the build-up with the quotation.

Time and cost together

  • Show the effect on the programme (critical path) at the same time as the cost; agreeing cost without time often leads to delay disputes later.
  • Track pending quotations: unpriced variations are a hidden risk to the final account.
  • Report the net effect monthly: agreed additions, omissions, pending items and time.
Good to knowNo instruction, no work, unless it's an emergency. And if it is an emergency, write it down the same day.