Earned Value

CPI, SPI and forecast at completion

Design data
ResultPreliminary · verify before design
Cost performance indexCPI 0.92SPI 0.88
Over limitOver budget and behind schedule
Cost variance (CV)-30,000
Schedule variance (SV)-50,000
Estimate at completion (EAC)1,085,714
Estimate to complete (ETC)705,714
Variance at completion (VAC)-85,714
TCPI1.05

Any currency. EAC assumes current cost performance continues.

What to verify before design ↓

Verify before using in design

  • Use one baseline and the same cut-off date for PV, EV and AC.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Oct 2026

Formula

CPI = EV ÷ AC SPI = EV ÷ PV EAC = BAC ÷ CPI

Standards and references

  • PMI Practice Standard for Earned Value Management (2nd ed.)
  • PMBOK Guide, 7th ed.

Assumptions

  • EAC = BAC ÷ CPI assumes current cost performance continues.

Inputs and units

Budget at completion (BAC)
Planned value (PV)
Earned value (EV)
Actual cost (AC)

Typical range: last column

Worked example (default values)

  • Budget at completion (BAC)1000000
  • Planned value (PV)400000
  • Earned value (EV)350000
  • Actual cost (AC)380000
Cost performance indexCPI 0.92Over budget and behind schedule

Next steps

More Project management calculators

Found an error? Tell us