Defects Period, Warranties & Retention

Taking over is not the end of the contract. For a year or more the contractor must fix defects, keep warranties alive and wait for the rest of the retention money. Managing this period well protects both the margin and the relationship.

The defects period

  • Under FIDIC it is the defects notification period (often 12 months from taking over); many contracts still call it the defects liability period (DLP).
  • The client notifies defects; the contractor inspects and fixes them within a reasonable time, at its cost if the work was at fault.
  • Keep a defects log with dates notified, inspected and closed, and the cause (workmanship, design, misuse or wear).

Warranties

  • Maker's warranties for major equipment (chillers, generators, lifts, UPS) are collected at handover with their start and end dates.
  • Check that the warranty start matches the contract: a chiller commissioned six months before taking over may lose half its warranty.
  • Many warranties require maintenance by authorised companies; tell the client in the O&M manual.

Retention and the final certificate

  • Retention money is deducted from each payment up to a limit; typically half is released at taking over and half after the defects period.
  • The performance certificate (FIDIC) is issued when the defects period ends and all defects are fixed; then the final statement and final payment follow.
  • A retention bond can sometimes replace cash retention; it must stay valid until release.
Good to knowDiary the end of every warranty and the defects period on the day of taking over. Missed dates cost money on both sides.