O&M Manuals, As-builts & Asset Data
After handover, the operators run the building from the documents you leave behind. Good O&M information is short, organised by system, matches what was installed, and can be found at 3 a.m. during a breakdown.
O&M manuals
- One manual per system, with a common structure: description, design data, operation, maintenance schedule, fault finding, spares, contacts.
- Include the approved material submittals, maker's manuals for the actual models installed and the test and commissioning records.
- Remove brochures for products you didn't install; they confuse operators.
- Deliver an electronic copy with bookmarks and searchable text, plus hard copies if the contract asks.
As-built drawings
- Collected continuously from site mark-ups, not drawn from memory at the end.
- Show actual routes, levels, sizes and equipment tags, especially for buried and concealed services.
- Panel schedules and circuit charts match the boards; valve and damper tags match the drawings.
- Verified and signed by the site team before submission.
Asset data
- An asset register lists every maintainable item: tag, description, system, location, maker, model, serial number, commissioning date and warranty.
- Some clients ask for COBie or a direct import into their CAFM system; agree the fields and tag format early.
- Planned preventive maintenance (PPM) frequencies come from the makers' manuals and the client's maintenance policy.
- Warranty start dates follow the contract: often taking-over, not commissioning.