Progress Measurement and Rules of Credit
Progress must be measured, not guessed. Agree the method for each kind of work before the first report, and keep it.
Methods
- Units completed: metres of cable pulled ÷ total metres.
- Weighted milestones (rules of credit): for example delivered 10 %, installed 60 %, connected 20 %, tested 10 %.
- Start / finish: 50 % at start, 100 % at finish, for short activities.
- Level of effort: supervision or management, progress follows time and is not used to show performance.
Weights
- Weight each activity by budget or man-hours from the baseline.
- Overall % = Σ(weight × % complete) ÷ Σ weights (Weighted Progress % calculator).
- Never change the weights to improve the curve.
Monthly report
- Planned vs actual S-curve, SPI and the main reasons for variance.
- Critical path, float change and forecast finish.
- Look-ahead, key issues and actions needed from the client, consultant and authorities.
Use with this guide
Progress Measurement by Weightage
Activities with weights and rules of credit, % complete from quantities, overall progress, planned vs actual by month and SPI
- How to use
- Progress
- Progress (SAMPLE)