Progress Measurement and Rules of Credit

Progress must be measured, not guessed. Agree the method for each kind of work before the first report, and keep it.

Methods

  • Units completed: metres of cable pulled ÷ total metres.
  • Weighted milestones (rules of credit): for example delivered 10 %, installed 60 %, connected 20 %, tested 10 %.
  • Start / finish: 50 % at start, 100 % at finish, for short activities.
  • Level of effort: supervision or management, progress follows time and is not used to show performance.

Weights

  • Weight each activity by budget or man-hours from the baseline.
  • Overall % = Σ(weight × % complete) ÷ Σ weights (Weighted Progress % calculator).
  • Never change the weights to improve the curve.

Monthly report

  • Planned vs actual S-curve, SPI and the main reasons for variance.
  • Critical path, float change and forecast finish.
  • Look-ahead, key issues and actions needed from the client, consultant and authorities.
Good to knowWrite the rules of credit into the progress procedure and get them approved before the first monthly report.

Use with this guide

CalculatorWeighted Progress %CalculatorForecast Finish from Progress
Free

Progress Measurement by Weightage

Activities with weights and rules of credit, % complete from quantities, overall progress, planned vs actual by month and SPI

  • How to use
  • Progress
  • Progress (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 21 Nov 2026 · blank template with a filled sample · check it against your project specification

ChecklistMonthly Progress Update
Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.