Forecast Finish from Progress

Forecast duration and delay from the progress rate so far

Design data
days
days
%
%
ResultPreliminary · verify before design
Forecast duration (SPI method)643 days103 days late against 540 planned
Over limitForecast delay over 10 %: recovery programme and notices needed
SPI (earned ÷ planned)0.84
Average progress rate so far0.156 %/day
Forecast duration at the average rate so far643 days
Remaining work at that rate373 days
Rate needed to finish on time0.215 %/day

A trend forecast only. The programme's critical path, not the overall %, decides the finish date: update the schedule and check the critical activities. Early progress is often slow, so the rate method is pessimistic in the first months.

What to verify before design ↓

Verify before using in design

  • Updated programme: critical path, float and the activities driving the finish.
  • Delay events and notices under the contract when a delay is forecast.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by a senior engineer · Nov 2026

Formula

Forecast (SPI) = planned duration ÷ SPI Forecast (rate) = elapsed + (100 − earned %) ÷ (earned % ÷ elapsed)

Standards and references

  • Earned schedule and SPI forecasting (AACE, PMI)
  • Approved baseline programme and S-curve

Assumptions

  • Progress continues at the same efficiency (SPI) or the same average rate as so far.

Inputs and units

Planned durationdays30–2000
Elapsed time at the data datedays1–2000
Actual progress (earned %)%1–100
Planned progress at the data date%1–100

Typical range: last column

Worked example (default values)

  • Planned duration540 days
  • Elapsed time at the data date270 days
  • Actual progress (earned %)42 %
  • Planned progress at the data date50 %
Forecast duration (SPI method)643 daysForecast delay over 10 %: recovery programme and notices needed

Next steps