Delay Analysis Methods: an Overview

An extension of time is granted for delay to completion caused by events the contractor is not responsible for. The method shows the link between the event and the completion date.

Main methods

  • As-planned vs as-built: compares the plan with what happened; simple, but weak at proving cause.
  • Impacted as-planned: adds the delay events to the baseline; shows potential delay, ignores actual progress.
  • Time impact analysis (TIA): inserts each event into the programme updated just before it; the common method for prospective extension of time.
  • Windows / time-slice analysis: studies the critical path period by period using the updates; strong for retrospective analysis.

What every method needs

  • An approved baseline and regular, honest updates.
  • Records: daily reports, letters, RFIs, instructions, photos.
  • Notices given on time under the contract.
  • Concurrent delays identified, not ignored.

References

  • The SCL Delay and Disruption Protocol and the AACE recommended practice on forensic schedule analysis describe these methods in detail; read them, this page is only a map.
Good to knowThe best delay analysis is built during the project from honest monthly updates and on-time notices, not after it ends.

Use with this guide

CalculatorForecast Finish from ProgressundefinedTopicCritical Path and FloatTopicVariations & Change Control
Free

Delay Event Register

Every delay event with dates, cause, responsible party, notice dates and time-bar warning, affected activities and days claimed

  • How to use
  • Register
  • Register (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 21 Nov 2026 · blank template with a filled sample · check it against your project specification

CalculatorProlongation Cost Estimate
Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.