Prolongation Cost Estimate

Time-related site overheads and head-office overhead for a delay

Design data
days
days
%
Settings & basis
ResultPreliminary · verify before design
Prolongation cost estimate584,444Site 540,000 + head office 44,444 for 30 days
Site overheads for the delay540,000
Head-office overhead and profit for the delay44,444
Head office per day1,481
Formula usedEmden (company accounts %)

Any currency. Only delay caused by the employer's risk events and on the critical path is normally compensable; concurrent delay may give time but not money. Site overheads should be the actual costs from records; head-office formulas need evidence that other work was lost. Not legal advice: follow your contract and the SCL Protocol guidance.

What to verify before design ↓

Verify before using in design

  • Actual time-related site costs from the cost records for the delay period.
  • Evidence that the delay stopped the company winning other work (for head-office claims).
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by a senior engineer · Nov 2026

Formula

Site = daily time-related cost × days Head office = (HO % ÷ 100) × contract sum ÷ contract period × days

Standards and references

  • Society of Construction Law Delay and Disruption Protocol (2nd edition)
  • Contract clauses on cost for employer delay

Assumptions

  • All delay entered is compensable and critical; head-office overhead recovered by a formula with the % from the source chosen.

Inputs and units

Time-related site overheads per day (staff, offices, plant, utilities)100–1000000
Compensable delaydays1–1000
Contract sum
Contract perioddays30–3000
Head-office overhead and profit%2–15
Head-office % taken from—

Typical range: last column

Worked example (default values)

  • Time-related site overheads per day (staff, offices, plant, utilities)18000
  • Compensable delay30 days
  • Contract sum10000000
  • Contract period540 days
  • Head-office overhead and profit8 %
  • Head-office % taken fromThe company's audited accounts (Emden formula)
Prolongation cost estimate584,444

Next steps

More Project management calculators