Extension of Time and Claims: the Basics
A claim asks for time, money or both because of an event the contract puts at the other party's risk. It succeeds on three things: entitlement under a clause, cause and effect, and records.
Time
- An extension of time moves the completion date and so protects against delay damages.
- Only delay to completion counts: show the effect on the critical path (Delay Analysis Methods).
- Concurrent delay: many contracts and the SCL Protocol give time but not money where both parties caused delay at the same time.
Money
- Prolongation: time-related site costs for the extended period, and head-office overhead where proved (Prolongation Cost Estimate).
- Disruption: lost productivity, shown by comparing affected and unaffected work.
- Acceleration: extra cost of finishing earlier than the entitled date, when instructed.
How claims are decided
- The engineer or contract administrator assesses first; then the contract's dispute route (a dispute board, adjudication, arbitration or courts).
- Well-organised claims with clear records settle earlier and for more.