Extension of Time and Claims: the Basics

A claim asks for time, money or both because of an event the contract puts at the other party's risk. It succeeds on three things: entitlement under a clause, cause and effect, and records.

Time

  • An extension of time moves the completion date and so protects against delay damages.
  • Only delay to completion counts: show the effect on the critical path (Delay Analysis Methods).
  • Concurrent delay: many contracts and the SCL Protocol give time but not money where both parties caused delay at the same time.

Money

  • Prolongation: time-related site costs for the extended period, and head-office overhead where proved (Prolongation Cost Estimate).
  • Disruption: lost productivity, shown by comparing affected and unaffected work.
  • Acceleration: extra cost of finishing earlier than the entitled date, when instructed.

How claims are decided

  • The engineer or contract administrator assesses first; then the contract's dispute route (a dispute board, adjudication, arbitration or courts).
  • Well-organised claims with clear records settle earlier and for more.
Good to knowBuild the claim file during the project, event by event. Claims prepared after completion are slower and weaker.