Delay Damages Exposure

Delay damages for days late, with the contract cap

Design data
%/day
% of price
days
days
ResultPreliminary · verify before design
Delay damages at the days entered450,00045 days × 10,000 per day
Within limitCap reached after 100 days
Damages per day10,000
Cap1,000,000
Days to reach the cap100
Days late after the expected extension25
Damages after the expected extension250,000
Saved by the extension of time200,000

Any currency. Rate, cap and whether damages apply per section come from the contract data. Delay damages are usually the employer's only remedy for late completion up to the cap; a granted extension of time moves the completion date. Not legal advice: read your contract.

What to verify before design ↓

Verify before using in design

  • Sectional completion rates and caps, if the contract has sections.
  • Extension of time claims and notices are up to date.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by a senior engineer · Nov 2026

Formula

Damages = min(rate × contract price × days, cap × contract price)

Standards and references

  • Contract data: delay damages rate and maximum (for example FIDIC 2017 Sub-Clause 8.8)
  • Applicable law on liquidated damages

Assumptions

  • Damages accrue per day of delay after the (extended) completion date, up to the cap; one rate for the whole works.

Inputs and units

Contract price
Daily delay damages rate%/day0.01–0.5
Maximum delay damages (cap)% of price1–20
Days late (after any extension of time)days0–1000
Days of extension of time you expect to be granteddays0–1000

Typical range: last column

Worked example (default values)

  • Contract price10000000
  • Daily delay damages rate0.1 %/day
  • Maximum delay damages (cap)10 % of price
  • Days late (after any extension of time)45 days
  • Days of extension of time you expect to be granted20 days
Delay damages at the days entered450,000Cap reached after 100 days