Estimate at Completion (4 Methods)

EAC by budget rate, CPI, CPI × SPI and bottom-up, side by side

Design data
ResultPreliminary · verify before design
Likely estimate at completion (CPI method)1,085,714Range 1,030,000 to 1,186,531 · VAC -85,714
Over limitOver budget; finishing on budget needs TCPI 1.05
EAC 1: remaining work at budget rate (AC + BAC − EV)1,030,000
EAC 2: current cost performance continues (BAC ÷ CPI)1,085,714
EAC 3: cost and schedule both affect the rest (CPI × SPI)1,186,531
EAC 4: bottom-up (AC + ETC)1,070,000
CPI / SPI0.92 / 0.88
To-complete performance index (TCPI to BAC)1.05

Any currency. Report the method you use and why: budget rate when the overrun was a one-off, CPI when it is a trend, CPI × SPI when the delay also costs money, bottom-up when the remaining work has been re-estimated. Same definitions as the PMBOK guide and the AACE practices, in our own words.

What to verify before design ↓

Verify before using in design

  • Accruals: work done but not yet invoiced is included in AC.
  • Approved variations added to BAC before comparing.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by a senior engineer · Nov 2026

Formula

EAC₁ = AC + (BAC − EV) EAC₂ = BAC ÷ CPI EAC₃ = AC + (BAC − EV) ÷ (CPI × SPI) EAC₄ = AC + ETC TCPI = (BAC − EV) ÷ (BAC − AC)

Standards and references

  • PMBOK guide: earned value management (definitions)
  • AACE International recommended practices on forecasting

Assumptions

  • Same currency and cut-off date for PV, EV and AC; ETC re-estimated from the remaining quantities when entered.

Inputs and units

Budget at completion (BAC)
Planned value (PV)
Earned value (EV)
Actual cost (AC)
Bottom-up estimate to complete (0 if none)

Typical range: last column

Worked example (default values)

  • Budget at completion (BAC)1000000
  • Planned value (PV)400000
  • Earned value (EV)350000
  • Actual cost (AC)380000
  • Bottom-up estimate to complete (0 if none)690000
Likely estimate at completion (CPI method)1,085,714Over budget; finishing on budget needs TCPI 1.05