The Cost Control Cycle: Budget, Commitment, Actual, Forecast

Cost control is not accounting. Accounting records what was spent; cost control forecasts what the job will cost in the end, early enough to act.

The four numbers per cost code

  • Budget: the approved allowance, plus approved changes.
  • Committed: orders and subcontracts placed, whether invoiced or not.
  • Actual: cost incurred to date, including accruals.
  • Forecast at completion: actual + estimate to complete; compare with budget for the variance.

Earned value

  • CPI = EV ÷ AC, SPI = EV ÷ PV (Earned Value calculator).
  • Forecast by more than one method and explain the choice (Estimate at Completion, 4 methods).

Habits that work

  • Same cut-off date for cost and progress.
  • Explain every variance above an agreed threshold.
  • Track contingency use and risks separately from the base cost.
  • Price and log every change as it happens, not at the final account.
Good to knowA forecast that has not changed for three months on a live project is usually not being updated.

Use with this guide

CalculatorEstimate at Completion (4 Methods)CalculatorEarned Value
Free

Cost Control Sheet

Budget, approved changes, committed, actual and forecast per cost code with variance, CPI and EAC flags

  • How to use
  • Cost report
  • Cost report (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 21 Nov 2026 · blank template with a filled sample · check it against your project specification

ChecklistMonthly Cost Report Before IssueCalculatorPrice Adjustment (Index Formula)
Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.