The Cost Control Cycle: Budget, Commitment, Actual, Forecast
Cost control is not accounting. Accounting records what was spent; cost control forecasts what the job will cost in the end, early enough to act.
The four numbers per cost code
- Budget: the approved allowance, plus approved changes.
- Committed: orders and subcontracts placed, whether invoiced or not.
- Actual: cost incurred to date, including accruals.
- Forecast at completion: actual + estimate to complete; compare with budget for the variance.
Earned value
- CPI = EV ÷ AC, SPI = EV ÷ PV (Earned Value calculator).
- Forecast by more than one method and explain the choice (Estimate at Completion, 4 methods).
Habits that work
- Same cut-off date for cost and progress.
- Explain every variance above an agreed threshold.
- Track contingency use and risks separately from the base cost.
- Price and log every change as it happens, not at the final account.