Price Adjustment (Index Formula)

Escalation on work done using a fixed part and cost indices

Design data
ResultPreliminary · verify before design
Price adjustment for the period32,000Factor Pn = 1.0640 (+6.40 %)
Within limitWeights add up to 1.00
Labour part10,500
Materials part24,000
Fuel / plant part-2,500
Adjusted value of the work532,000

Any currency. Only applies if the contract has a price-adjustment clause with a formula; the fixed part, the weights, the indices and their source and the base date are stated in the contract data. Many fixed-price contracts in the region have no adjustment.

What to verify before design ↓

Verify before using in design

  • Base date, index source and weights from the contract data.
  • Delays caused by the contractor: indices may be frozen at the planned completion date.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by a senior engineer · Nov 2026

Formula

Pn = a + b·(Ln ÷ Lo) + c·(Mn ÷ Mo) + d·(Fn ÷ Fo) Adjustment = value × (Pn − 1)

Standards and references

  • Contract price-adjustment clause and its formula (for example FIDIC 2017 Sub-Clause 13.7, in contracts that include it)
  • Official cost indices named in the contract data

Assumptions

  • Indices taken at the date stated in the contract; value at base prices excluding items already adjusted.

Inputs and units

Value of work in the period (at base prices)
Fixed (non-adjustable) part a0–0.35
Labour weight b0–1
Labour index: current ÷ base0.5–2
Materials weight c0–1
Materials index: current ÷ base0.5–2
Fuel / plant weight d0–1
Fuel / plant index: current ÷ base0.5–2

Typical range: last column

Worked example (default values)

  • Value of work in the period (at base prices)500000
  • Fixed (non-adjustable) part a0.15
  • Labour weight b0.35
  • Labour index: current ÷ base1.06
  • Materials weight c0.4
  • Materials index: current ÷ base1.12
  • Fuel / plant weight d0.1
  • Fuel / plant index: current ÷ base0.95
Price adjustment for the period32,000Weights add up to 1.00

Next steps

More Project management calculators

Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.