Contractor Cash Flow & Peak Funding

Monthly cost against receipts with advance, retention and payment delay

Design data
months
%
% of value
% of each payment
months
Settings & basis
ResultPreliminary · verify before design
Peak funding needed1,944,444Lowest cash position in month 8
Over limitFunding gap 19.4 % of the contract value: arrange finance or better payment terms
Cost of the works9,259,259
Advance received at start1,000,000
Retention held at the end1,000,000
Cash position at the last payment (before retention release)-259,259
Cash position after month 3-219,690
Cash position after month 6-1,629,630
Cash position after month 9-1,867,996

Any currency. The advance is recovered from each payment in proportion to the value; retention is released after completion and the defects period (Retention Money & Release). Real cash flow needs the payment terms, supplier credit and the cost-loaded programme.

What to verify before design ↓

Verify before using in design

  • Supplier and subcontractor payment terms (they reduce the funding gap).
  • Real certification and payment periods, not only the contract periods.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by a senior engineer · Nov 2026

Formula

Cost each month = cost × Δ(spend curve); receipt = value of the work certified (lag months earlier) × (1 − retention − advance recovery)

Standards and references

  • Contract payment terms (advance, retention, payment period)
  • Cost-loaded baseline programme

Assumptions

  • Cost spread on the chosen profile; each month certified at value and paid after the delay; advance recovered in proportion to value; retention released after the period shown.

Inputs and units

Contract value
Construction durationmonths1–60
Margin (value above cost)%0–25
Advance payment% of value0–30
Retention% of each payment0–10
Payment delay after the month's workmonths0–6
Spend profile—

Typical range: last column

Worked example (default values)

  • Contract value10000000
  • Construction duration12 months
  • Margin (value above cost)8 %
  • Advance payment10 % of value
  • Retention10 % of each payment
  • Payment delay after the month's work2 months
  • Spend profileS-curve (slow start, peak in the middle)
Peak funding needed1,944,444Funding gap 19.4 % of the contract value: arrange finance or better payment terms