Cash Flow: Why Profitable Projects Run Out of Cash
A contractor pays for labour, materials and subcontractors before the client pays for the work. The gap between the two, not the margin, decides how much finance a project needs.
What drives the gap
- Payment delay: valuation, certification and payment periods add up to 2–3 months or more.
- Retention: often 5–10 % held until completion and the defects period.
- Front-loaded costs: mobilisation, temporary works and early procurement.
- Unapproved variations: work done but not certified.
What reduces it
- An advance payment against a bank guarantee.
- Supplier and subcontractor terms matched to the client's payment terms.
- Prompt monthly applications with full backup.
- Pricing and approving variations early.