Late Payment Financing Charges

Charges on an amount paid late at an annual rate

Design data
days
%/year
Settings & basis
ResultPreliminary · verify before design
Financing charges18,08275 days at 8.00 % a year (simple)
Charge per day241
Total with the amount1,118,082
Effective rate for the period1.644 %

Any currency. The rate and method come from the contract (for example a margin above a central-bank rate, compounded monthly in FIDIC 2017 Sub-Clause 14.8) or the applicable law. Some countries limit or do not allow interest on late payment; check locally. Not legal advice.

What to verify before design ↓

Verify before using in design

  • Rate, compounding and the date from which charges run, from the contract.
  • Whether interest is allowed under the governing law.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by a senior engineer · Nov 2026

Formula

Simple: A × r × days ÷ basis Monthly compounding: A × ((1 + r ÷ 12)^(12 × days ÷ basis) − 1)

Standards and references

  • Contract clause on delayed payment (for example FIDIC 2017 Sub-Clause 14.8)
  • Applicable law on interest

Assumptions

  • One amount paid late by the days entered at a constant annual rate.

Inputs and units

Amount paid late
Days latedays1–730
Annual financing rate%/year1–20
Day basis—
Compounding—

Typical range: last column

Worked example (default values)

  • Amount paid late1100000
  • Days late75 days
  • Annual financing rate8 %/year
  • Day basis365 days
  • CompoundingSimple
Financing charges18,082