Notices and Time Bars: Why the Deadline Matters

Many contracts say a claim for time or money is lost if notice is not given within a set period. In FIDIC 2017, for example, the period is 28 days from when the party became aware, or should have become aware, of the event. Courts in some countries enforce these clauses strictly.

What to do

  • List every notice clause and its period at contract award (Contract Review on Award).
  • Log every event the day it happens and the date the notice falls due (Delay Event Register).
  • Send a short notice in time; details can follow within the contract's period for particulars.
  • Keep records from day one: daily reports, photos, letters, minutes.

Common mistakes

  • Waiting to quantify the delay before notifying.
  • Relying on minutes of meeting or emails when the contract requires a formal notice.
  • Sending to the wrong person or address.

Note

  • General guidance, not legal advice. Notice rules differ by contract and by law; read your contract and take advice on important claims.
Good to knowSend the notice first and do the analysis after. A late perfect notice can be worth nothing.

Use with this guide

Free

Delay Event Register

Every delay event with dates, cause, responsible party, notice dates and time-bar warning, affected activities and days claimed

  • How to use
  • Register
  • Register (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 21 Nov 2026 · blank template with a filled sample · check it against your project specification

TemplateNotice of Delay EventChecklistBefore Sending a Contractual LetterTopicFIDIC Rainbow: Red, Yellow, SilverCalculatorLate Payment Financing Charges