Interim Payment Application (Net Due)

Gross value less retention, advance recovery and previous payments

Design data
%
% of price
% of gross
%
ResultPreliminary · verify before design
Net amount due this period500,000Cumulative net 3,600,000 less previous 3,100,000
Within limitPositive amount due
Gross cumulative value4,500,000
Retention (limited)450,000
Retention limit reachedNo
Advance recovered to date450,000
Advance still to recover550,000
Cumulative net value3,600,000

Any currency. Cumulative method, the usual way interim payments are certified. Retention limit, advance recovery rule, materials on site rules, other deductions (delay damages, back-charges) and tax follow the contract; the certifier may adjust the amounts.

What to verify before design ↓

Verify before using in design

  • Advance recovery rule in the contract (some start at a % of progress and finish before completion).
  • Materials on site: ownership, storage and vesting conditions met.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by a senior engineer · Nov 2026

Formula

Net due = (work + variations + materials) − retention (limited) − advance recovery − previous payments

Standards and references

  • Contract payment clauses (for example FIDIC 2017 Clause 14)
  • Bill of quantities and approved variations

Assumptions

  • Cumulative valuation; retention at the given % up to the limit; advance recovered at a fixed % of each gross amount until repaid.

Inputs and units

Cumulative value of permanent work done
Cumulative approved variations
Materials on site (eligible)
Retention%0–10
Retention limit% of price0–10
Accepted contract price
Advance payment received
Advance recovery% of gross0–30
Total of previous payment certificates (net)
VAT / sales tax%0–15

Typical range: last column

Worked example (default values)

  • Cumulative value of permanent work done4200000
  • Cumulative approved variations180000
  • Materials on site (eligible)120000
  • Retention10 %
  • Retention limit5 % of price
  • Accepted contract price10000000
  • Advance payment received1000000
  • Advance recovery10 % of gross
  • Total of previous payment certificates (net)3100000
  • VAT / sales tax0 %
Net amount due this period500,000Positive amount due