BOQ Quantity Change & Rate Review

Measured vs BOQ quantity, value change and whether a new rate may be reviewed

Design data
%
% of contract
%
%
ResultPreliminary · verify before design
Value change at the BOQ rate23,00020.8 % quantity change (250.00 units)
ReviewQuantity and value limits passed, but the cost per unit change is within its limit: the BOQ rate normally stays
BOQ value110,400
Measured value at the BOQ rate133,400
Value change limit1,000
Quantity testPassed
Value testPassed
Cost per unit testNot passed

Any currency and unit. For re-measured contracts only: in a lump-sum contract quantities are usually not re-measured. Some contracts (for example FIDIC 1999 and 2017 Sub-Clause 12.3) allow a new rate only when several tests like these are all passed and the item is not a fixed-rate item; others never change rates for quantity. Enter the limits from your contract. A quantity change caused by an instruction is a variation, valued under the variation clause. Not legal advice.

What to verify before design ↓

Verify before using in design

  • The limits written in your contract (they differ between contracts and editions).
  • The measured quantity agreed with the engineer, from drawings or site measurement.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by a senior engineer · Nov 2026

Formula

Value change = (measured − BOQ quantity) × rate Tests: |Δq| > quantity limit · |value change| > value limit × contract amount · |cost per unit change| > its limit

Standards and references

  • FIDIC 1999 / 2017 Red Book Sub-Clause 12.3 (evaluation of new rates; clause number only)
  • Your contract's measurement and valuation clauses

Assumptions

  • Re-measured contract; the item is not a fixed-rate or lump-sum item; the quantity change is not caused by a variation instruction.

Inputs and units

BOQ quantity
Measured or instructed quantity
BOQ unit rate
Accepted contract amount
Quantity change limit%0–100
Value change limit% of contract0–5
Change in your cost per unit caused by the quantity change (your estimate)%-100–100
Cost per unit change limit%0–50

Typical range: last column

Worked example (default values)

  • BOQ quantity1200
  • Measured or instructed quantity1450
  • BOQ unit rate92
  • Accepted contract amount10000000
  • Quantity change limit10 %
  • Value change limit0.01 % of contract
  • Change in your cost per unit caused by the quantity change (your estimate)0 %
  • Cost per unit change limit1 %
Value change at the BOQ rate23,000Quantity and value limits passed, but the cost per unit change is within its limit: the BOQ rate normally stays