How to Read a Bill of Quantities (BOQ)
The BOQ lists the work as measured items with quantities and rates. It looks like a price list, but it is a contract document with its own rules: what each rate includes, how quantities are measured, and how special items are paid.
Read these parts first
- Preambles: general rules, what rates are deemed to include (labour, materials, plant, waste, overheads, profit), and how to price.
- Method of measurement: the named standard or project rules that say how each item is measured (net, laps and waste included in the rate, and so on).
- Preliminaries / general items: site establishment, staff, insurances, temporary works; often split into fixed and time-related.
Special item types
- Provisional sum: an amount for work not yet defined; spent only on the engineer's instruction and adjusted to the actual value.
- Prime cost (PC) sum: an amount for a supply by a nominated supplier or subcontractor; you usually add your attendance and profit.
- Optional item: priced by you, done only if the employer instructs it; then paid at your tendered rate, otherwise omitted with no compensation.
- Alternative item: a different way to do the same work; if chosen it replaces the original item.
- Daywork: rates for labour, plant and materials used for small unforeseen work on a time basis.
- Rate-only item: a rate with no quantity, used if the work is needed.
Re-measured or lump sum
- Re-measured: you are paid the measured quantity at the BOQ rate; quantity errors are the employer's risk.
- Lump sum: the price covers the whole work shown; quantities in the BOQ may be for information only, so quantity errors are often your risk.
- The preambles and conditions of contract tell you which one applies; never assume.