Variation Orders: When You Are Entitled, and Optional Items

Not every change is a variation, and not every variation is paid. Before you price it, check that the change is outside the contract, properly instructed, not your own fault, within the contract's scope and notified in time.

The six questions

  • Is it a change? Compare with all the contract documents; 'deemed included' wording and lump-sum pricing reduce what counts as extra.
  • Who instructed it? Only the person the contract authorises (under FIDIC, the Engineer, Clause 13), in writing. Confirm verbal instructions in writing in time.
  • Whose cause? Your own error, your own design (design-build) or correcting rejected work is not a variation.
  • Does it fit the project? A variation must stay within the nature of the works. Completely different work may be outside the power to vary and need a new agreement. Some contracts let you object in set cases (for example materials you cannot obtain, or safety).
  • Notice in time? Check notice periods and time bars.
  • How is it valued? See below.

Valuation order

  • BOQ rates where the work is of similar character and done in similar conditions.
  • Rates derived from BOQ rates (pro rata) where it is similar but conditions differ.
  • A new rate built from cost plus overheads and profit (Unit Rate Build-up) where nothing similar exists; daywork for small work if the contract allows.
  • Include the effect on time and on other work, and the cost of disruption, with records.

Optional, provisional and alternative items

  • Optional item: you priced it, the employer decides. If instructed, it is paid at your tendered rate (usually not a new variation); if not, it is omitted with no claim. It is often outside the contract sum or in a separate schedule.
  • Provisional sum: an allowance for undefined work, spent only on instruction and adjusted to the real value.
  • Alternative item: replaces the original item if chosen.
  • Your BOQ preambles give the exact meaning on your project: always read them.
Good to knowNever start extra work on a verbal instruction without sending a written confirmation the same day.

Use with this guide

ChecklistIs It a Variation?ChecklistVariation Submission CheckTopicVariations & Change ControlCalculatorUnit Rate Build-up
Free

Site Instruction Register

Every instruction with date, source, written or verbal, confirmation sent, variation yes / no / to check, notice due and sent, and VO reference

  • How to use
  • Register
  • Register (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 21 Nov 2026 · blank template with a filled sample · check it against your project specification

TemplateConfirmation of Verbal Instruction
Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.