Transformer Fault Level

Full-load and short-circuit current

Design data
kV
kV
%
kA
Settings & basis
ResultPreliminary · verify before design
Maximum LV fault current43.3 kAc = 1.05, impedance at −10.0 % tolerance, infinite source
Within limit50 kA switchgear is adequate
Fault current, nameplate Z, c = 1.0539.0 kA
Fault current, nameplate Z, no c factor37.1 kA
Full-load current, LV2,226 A
Full-load current, MV84.0 A
Fault MVA (nameplate Z)26.7 MVA
Next standard ACB frame2500 A

Infinite upstream source and no motor contribution. c = 1.05 covers the LV voltage tolerance; the −10 % is the impedance tolerance allowed for transformers with Z below 10 %. A real utility source lowers the fault current; motors raise it. Use IEC 60909 software for the final study.

What to verify before design ↓

Verify before using in design

  • Get the utility fault level and include cable impedance (Fault Current at Cable End).
  • Switchgear Icu / Icw must exceed the fault current.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Oct 2026✓ Tested against worked examples✓ Reviewed by an electrical engineer · Nov 2026

Formula

FLC = S ÷ (√3 · Un) Ik,max = c · FLC ÷ (Z% · (1 − tolerance))

Standards and references

  • IEC 60909-0:2016 (simplified method)
  • IEC 60076-5 (transformer short-circuit)

Assumptions

  • Infinite upstream source: only transformer impedance limits the fault.
  • Voltage factor c applied (IEC 60909-0) and impedance reduced by its tolerance (IEC 60076-1: −10 % below 10 % Z, −7.5 % above).
  • No motor contribution; impedance at rated tap.

Inputs and units

RatingkVA
Primary voltagekV3.3–33
Secondary voltagekV0.2–1
Impedance%3–10
Switchgear ratingkA
Voltage factor c (IEC 60909)—

Typical range: last column

Worked example (default values)

  • Rating1600 kVA
  • Primary voltage11 kV
  • Secondary voltage0.415 kV
  • Impedance6 %
  • Switchgear rating50 kA
  • Voltage factor c (IEC 60909)1.05 · LV, +6 % tolerance
Maximum LV fault current43.3 kA50 kA switchgear is adequate