Fault Current at Cable End

Short-circuit current at a remote board

Design data
V
kA
m
cannot exceed 0.5
Settings & basis
Result
Check the inputs
  • Source X/R ratio: cannot exceed 0.5

Verify before using in design

  • Use this for breaking capacity. For protection and disconnection checks use the minimum fault current: IEC 60228 maximum resistance corrected to the hot conductor temperature, and the earth fault loop (see the Zs calculator).
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.1 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by an electrical engineer · Nov 2026

Formula

Zsource = c · V ÷ (√3 · Is) I = c · V ÷ (√3 · |Zsource + Zcable|)

Standards and references

  • IEC 60909-0:2016 (simplified)

Assumptions

  • Bolted three-phase fault; cold conductors at 20 °C (maximum fault current).
  • Cable resistance from ρ = 0.0178 Ω·mm²/m (Cu), 0.0286 (Al). This is a little below the IEC 60228 maximum values (e.g. 95 mm² Cu: 0.187 vs 0.193 mΩ/m), so the fault current comes out about 1–2 % higher: on the safe side for breaking capacity.
  • Voltage factor c applied to source and result (IEC 60909-0).
  • Cable reactance 0.08 mΩ/m.
  • Source impedance split into R and X with the X/R ratio you enter (default 10). Use the value from the utility or the transformer data; a lower X/R gives a lower result at the cable end.

Inputs and units

Line voltageV200–1000
Fault level at sourcekA
Cable lengthm
Conductor sizemm²
Material—
Voltage factor c—
Source X/R ratio1–20

Typical range: last column

Worked example (default values)

  • Line voltage400 V
  • Fault level at source37 kA
  • Cable length60 m
  • Conductor size95 mm²
  • MaterialCopper
  • Voltage factor c1.05
  • Source X/R ratio10
Fault current at cable end14.8 kA

Next steps

More Electrical calculators

Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.