Earth Conductor Size

Adiabatic check for protective conductors

Design data
kA
s
Settings & basis
ResultPreliminary · verify before design
Minimum size44.2 mm²Select 50 mm²
k factor143
I²t energy40.0 × 10⁶ A²s

Use the actual fault current at the circuit end and the device's real disconnection time.

What to verify before design ↓

Verify before using in design

  • Use the fault current at the circuit end and the device's real disconnection time.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Oct 2026✓ Tested against worked examples✓ Reviewed by an electrical engineer · Nov 2026

Formula

S = √(I² t) ÷ k (IEC 60364-5-54 / BS 7671 543.1.3)

Standards and references

  • IEC 60364-5-54:2011
  • BS 7671:2018+A3:2024, Regulation 543.1.3

Assumptions

  • Adiabatic equation: no heat lost during the fault.

Inputs and units

Fault currentkA
Disconnection times0.01–5
Conductor type—

Typical range: last column

Worked example (default values)

  • Fault current10 kA
  • Disconnection time0.4 s
  • Conductor typeCopper core in XLPE cable · k 143
Minimum size44.2 mm²

Next steps