UPS & Battery

UPS rating and battery Ah for autonomy

Design data
kVA
min
Settings & basis
ResultPreliminary · verify before design
Battery capacity (10-hour rating)82 Ahat 480 V DC for 15 min
Load in kW54.0 kW
Energy from battery14.2 kWh
Ah actually drawn30 Ah
Discharge-rate factor Kt (typical VRLA, 15 min)0.45
Battery current at start118 A
Required UPS (20 % growth)72 kVA
Next standard UPS size80 kVA
12 V blocks per string40

Kt is a typical value for VRLA batteries, not one maker's data. Final selection uses the battery maker's constant-power discharge tables (W per cell to the end voltage).

What to verify before design ↓

Verify before using in design

  • Final sizing uses the battery maker's constant-power tables and end voltage per cell.
  • Hot battery rooms shorten life: confirm cooling.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.1 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by an electrical engineer · Nov 2026

Formula

Ah (10 h) = P · t ÷ (Vdc · η) × ageing ÷ Kt

Standards and references

  • IEC 62040-3 (UPS performance)
  • IEEE 1184 (batteries for UPS)

Assumptions

  • Constant power discharge; battery at 20–25 °C.
  • Ageing factor 1.25 for end-of-life capacity.
  • Discharge-rate factor Kt: share of the 10-hour capacity a VRLA battery gives when emptied in the autonomy time, to 1.67 V/cell (typical values: 5 min 0.30, 15 min 0.45, 30 min 0.56, 60 min 0.65, 120 min 0.75).

Inputs and units

Critical loadkVA
Load PF0.7–1
Autonomymin5–120
DC bus voltageV
Inverter efficiency0.85–0.98
Ageing factor1–1.4

Typical range: last column

Worked example (default values)

  • Critical load60 kVA
  • Load PF0.9
  • Autonomy15 min
  • DC bus voltage480 V
  • Inverter efficiency0.95
  • Ageing factor1.25
Battery capacity (10-hour rating)82 Ah

Next steps

More Electrical calculators

Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.