PF Correction

Capacitor bank size to reach target PF

Design data
kW
Settings & basis
ResultPreliminary · verify before design
Required compensation236.8 kVArInstall 250.0 kVAr (10 × 25 kVAr steps)
kVA before641 kVA
kVA after526 kVA
kVA released115 kVA
Current reduction17.9 %

Use detuned reactors where VFDs or UPS create harmonics.

What to verify before design ↓

Verify before using in design

  • Run a harmonic study; use detuned reactors (7 % or 14 %) where VFDs, UPS or LED drivers are present. Plain capacitors can resonate with the transformer and amplify harmonics.
  • Confirm the utility's minimum power factor requirement.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Oct 2026✓ Reviewed by an electrical engineer · Nov 2026

Formula

Qc = P · (tan φ₁ − tan φ₂)

Standards and references

  • IEC 61921:2017 (PFC banks)
  • IEC 60831-1 (LV shunt capacitors)

Assumptions

  • Constant load; no harmonic resonance.

Inputs and units

Active loadkW
Existing PF0.5–0.99
Target PF0.8–1
Step sizekVAr

Typical range: last column

Worked example (default values)

  • Active load500 kW
  • Existing PF0.78
  • Target PF0.95
  • Step size25 kVAr
Required compensation236.8 kVAr