Thrust Block Bearing Area

Thrust at a bend, tee or end of a pressure main and the block face area

Design data
mm
bar
kPa
Settings & basis
ResultPreliminary · verify before design
Bearing area of the block face2.65 m²Thrust 176.3 kN × safety factor 1.5 on 100 kPa
Resultant thrust176.3 kN
Pressure × pipe area (P·A)124.7 kN
Square face side1.63 m
Thrust directionOutward, on the bisector of the bend

Uses the test pressure and the outside diameter (conservative). The block must bear against undisturbed ground; the allowable bearing comes from the site investigation. Vertical bends, restrained joints instead of blocks, and blocks near other services or excavations need the designer's check.

What to verify before design ↓

Verify before using in design

  • Allowable horizontal bearing from the soil report; reduce near excavations or other services.
  • Block concrete, reinforcement and curing time before the pressure test.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by a senior engineer · Nov 2026

Formula

Bend: T = 2·P·A·sin(θ ÷ 2) Tee / end: T = P·A Face area = T·SF ÷ q

Standards and references

  • AWWA M41 / M23 (thrust restraint for pressure pipes)
  • Pipe maker's thrust restraint guide
  • Site investigation (allowable bearing)

Assumptions

  • Thrust from the test pressure on the outside-diameter area; block bears on undisturbed ground; friction on the block ignored.

Inputs and units

Fitting—
Pipe outside diametermm50–1600
Test pressurebar1–40
Allowable soil bearing (horizontal)kPa25–400
Safety factor1–2

Typical range: last column

Worked example (default values)

  • FittingBend 90°
  • Pipe outside diameter315 mm
  • Test pressure16 bar
  • Allowable soil bearing (horizontal)100 kPa
  • Safety factor1.5
Bearing area of the block face2.65 m²