Utilities & infrastructure

Testing and Commissioning of Utility Networks

Each utility owner accepts a network only after its own tests, witnessed and recorded. Plan the tests by section, so the road works are not held up.

Typical tests

  • Gravity sewer and storm: air or water test between manholes, CCTV survey, deflection check for flexible pipes, manhole leak test.
  • Water and TSE mains: hydrostatic pressure test, flushing, disinfection and bacteriological samples (water).
  • Power cables: insulation resistance, sheath test, high-voltage test for MV, phasing and continuity.
  • Telecom and ITS ducts: mandrel (proving) test, draw rope check; fibre loss and OTDR after cabling.
  • Compaction: field density tests on each backfill layer.

Plan the testing

  • A test tracker by section and chainage, with the planned date, the witness and the result.
  • Test before the road layers close the trench; re-opening a finished road costs far more than waiting a day.
  • Calibrated instruments with certificates on site for every test.
  • Agree the test method and acceptance values in writing before the first test.
Good to knowA failed test found before the road is built costs an hour; found after, it costs a road closure.

Use with this guide

Free

Network Test Tracker by Section

Pressure, air, CCTV, mandrel and compaction tests per section with dates, witness, result and progress per network

  • How to use
  • Tests
  • Tests (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 21 Nov 2026 · blank template with a filled sample · check it against your project specification

ChecklistSewer CCTV Survey & Air TestChecklistWater Main Pressure Test & DisinfectionCalculatorThrust Block Bearing AreaCalculatorStorm Water Flow (Rational Method)
Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.