TAB Airflow Check

Duct traverse or terminal airflow vs design and tolerance

Design data
L/s
m/s
mm
mm
%
%
ResultPreliminary · verify before design
Measured airflow480 L/s96.0 % of design (1,728 m³/h)
Within limitWithin −10 % / +10 % of design
Duct free area0.1200 m²
Velocity needed for design flow4.17 m/s
Difference from design-20 L/s

Average velocity from a proper pitot or anemometer traverse (log-Tchebycheff or equal-area points) in a straight duct run, away from bends and dampers. Tolerances come from your specification.

What to verify before design ↓

Verify before using in design

  • Use the tolerance band in the specification and record the instrument and its calibration date.
  • Check the fan curve and system static pressure before adjusting many terminals.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Oct 2026✓ Tested against worked examples

Formula

Q = v × A A = W × H (rectangular) or π D² ÷ 4 (round)

Standards and references

  • CIBSE Commissioning Code A (air distribution systems)
  • BSRIA BG 49 (commissioning air systems)
  • ASHRAE Standard 111 (TAB measurement)

Assumptions

  • Average velocity is the mean of a full traverse across the duct section.
  • Free area equals the inside duct dimensions (no lining or obstruction).

Inputs and units

Design airflowL/s
Average measured velocitym/s1–15
Duct width (or diameter)mm
Duct height (0 for round)mm
Lower tolerance%3–15
Upper tolerance%3–15

Typical range: last column

Worked example (default values)

  • Design airflow500 L/s
  • Average measured velocity4 m/s
  • Duct width (or diameter)400 mm
  • Duct height (0 for round)300 mm
  • Lower tolerance10 %
  • Upper tolerance10 %
Measured airflow480 L/sWithin −10 % / +10 % of design

Next steps

More Mechanical & HVAC calculators

Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.