Contract Clause Map: Where to Look (FIDIC 2017)
Clause numbers below are for the FIDIC 2017 Red and Yellow Books (Silver is similar). Other editions and forms use different numbers, and particular conditions may change them, so always check your own contract. Clause titles are summarised in our own words.
Time
- Clause 8: commencement, programme (8.3), extension of time (8.5), delay damages (8.8), suspension by the employer (8.9).
- Clause 9 and 10: tests on completion and taking over.
Money
- Clause 12: measurement and valuation (re-measured contracts).
- Clause 13: variations and adjustments, including changes in laws and cost.
- Clause 14: price and payment: advance (14.2), statements (14.3), certificates (14.6), payment (14.7), late payment (14.8), retention release (14.9), final statement.
People, quality and risk
- Clause 3: the Engineer, instructions and determinations. Clause 4: the contractor's general obligations, performance security (4.2), unforeseeable physical conditions. Clause 5: subcontracting. Clause 6: staff and labour.
- Clause 7: plant, materials and workmanship, testing. Clause 11: defects after taking over.
- Clause 17: care of the works and indemnities. Clause 18: exceptional events. Clause 19: insurance.
Ending and disputes
- Clause 15: termination by the employer. Clause 16: suspension and termination by the contractor.
- Clause 20: claims by either party (notice within 28 days, then a fully detailed claim).
- Clause 21: disputes: DAAB, amicable settlement, arbitration.
Use with this guide
Contract Abstract & Obligations Register
One page of key contract data (dates, amounts, delay damages, retention, advance, securities, insurances) with worked-out dates, and a register of every obligation with clause, deadline and overdue warnings