Project management

How to Read a Construction Contract

A construction contract is a set of documents, not one book. Reading it well means knowing which document wins when they disagree, where the project-specific changes are, and how a few key words change who carries a risk.

The documents

  • Contract agreement and letter of acceptance (price, dates, parties).
  • Particular conditions: contract data (the numbers: periods, rates, caps, percentages) and special provisions (changes to the general conditions).
  • General conditions: the standard form (for example FIDIC).
  • Specification, drawings, BOQ and schedules; the tender, if listed.

How to read it

  • Find the order of precedence clause first (FIDIC: Sub-Clause 1.5).
  • Read the particular conditions next to the general conditions, clause by clause: the special provisions often delete or rewrite whole clauses.
  • Read the definitions: 'Cost', 'Day', 'Works', 'Unforeseeable' and others have contract meanings.
  • Make a contract abstract: key data and every obligation with its deadline (Contract Abstract & Obligations Register).

Words that matter

  • shall: an obligation; may: a right or option.
  • deemed: treated as true even if it is not (for example 'deemed to have inspected the site').
  • sole cost, at no extra cost: no payment for it.
  • time is of the essence, condition precedent: missing a deadline can lose the right.
  • fitness for purpose: a higher design duty than reasonable skill and care.
Good to knowRead the particular conditions first, with a highlighter. That is where your project differs from every other project on the same form.

Use with this guide

ChecklistFirst Read of a New Contract
Free

Contract Abstract & Obligations Register

One page of key contract data (dates, amounts, delay damages, retention, advance, securities, insurances) with worked-out dates, and a register of every obligation with clause, deadline and overdue warnings

  • How to use
  • Abstract
  • Obligations
  • Abstract (SAMPLE)
  • Obligations (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 21 Nov 2026 · blank template with a filled sample · check it against your project specification

TopicContract Clause Map: Where to Look (FIDIC 2017)TopicTypes of Construction Contracts and How They DifferChecklistContract Review on Award
Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.