How to Read a Construction Contract
A construction contract is a set of documents, not one book. Reading it well means knowing which document wins when they disagree, where the project-specific changes are, and how a few key words change who carries a risk.
The documents
- Contract agreement and letter of acceptance (price, dates, parties).
- Particular conditions: contract data (the numbers: periods, rates, caps, percentages) and special provisions (changes to the general conditions).
- General conditions: the standard form (for example FIDIC).
- Specification, drawings, BOQ and schedules; the tender, if listed.
How to read it
- Find the order of precedence clause first (FIDIC: Sub-Clause 1.5).
- Read the particular conditions next to the general conditions, clause by clause: the special provisions often delete or rewrite whole clauses.
- Read the definitions: 'Cost', 'Day', 'Works', 'Unforeseeable' and others have contract meanings.
- Make a contract abstract: key data and every obligation with its deadline (Contract Abstract & Obligations Register).
Words that matter
- shall: an obligation; may: a right or option.
- deemed: treated as true even if it is not (for example 'deemed to have inspected the site').
- sole cost, at no extra cost: no payment for it.
- time is of the essence, condition precedent: missing a deadline can lose the right.
- fitness for purpose: a higher design duty than reasonable skill and care.
Use with this guide
Contract Abstract & Obligations Register
One page of key contract data (dates, amounts, delay damages, retention, advance, securities, insurances) with worked-out dates, and a register of every obligation with clause, deadline and overdue warnings