Types of Construction Contracts and How They Differ
Two contracts for the same building can share risk in opposite ways. Know the type of your contract before you price, plan your records or argue a claim.
By how you are paid
- Lump sum: fixed price for the defined work; the contractor carries quantity risk. Good when the design is complete.
- Re-measured (BOQ): measured quantity × BOQ rate; the employer carries quantity risk. Common for infrastructure.
- Unit rate / framework: agreed rates, work ordered as needed; maintenance and call-off work.
- Cost-plus (reimbursable): actual cost plus a fee; the employer carries most risk; needs strict cost records.
- Target cost: cost plus fee, with overrun or saving shared by an agreed formula (NEC4 Options C and D).
- Guaranteed maximum price: cost plus fee up to a cap; above the cap the contractor pays.
By who designs
- Traditional (design-bid-build): the employer's consultant designs, the contractor builds (FIDIC Red).
- Design and build: the contractor designs to the employer's requirements (FIDIC Yellow); design errors become the contractor's risk.
- EPC / turnkey: the contractor takes most risks for a fixed price and time (FIDIC Silver).
- Management contracting / construction management: a manager coordinates separate trade packages.
- PPP / BOT: the private party designs, builds, finances and operates for many years.
Standard forms you will meet
- FIDIC: Red, Yellow, Silver, Green (short form), Gold (design-build-operate), Emerald (underground works), White (consultants) and the subcontract form.
- NEC4: main Options A to F set the pricing, from lump sum to cost reimbursable.
- JCT: UK building contracts.
- Government forms: many public projects in the region use their own standard contracts, often based on FIDIC with heavy changes: read the particular conditions closely.
- Subcontracts: check whether they are back-to-back with the main contract (notices, payment, defects).
What to do differently
- Lump sum: check drawings against quantities at tender; record every change of scope.
- Re-measured: keep measurement records agreed with the engineer every month.
- Cost-plus and target cost: keep clean cost records by cost code; agree what counts as cost.
- Design and build: control your design and its approvals as tightly as construction.