Manhole Depths & Invert Levels

Invert levels, depths and cover along a gravity sewer line

Design data
m
%
m
m
%
mm
m
m
ResultPreliminary · verify before design
Deepest manhole2.20 mMH5; least cover 1.50 m at MH1
Within limitCover and depth within the limits entered
MH1 · ch 0 mGL 11.000 · IL 9.200 · depth 1.80 m
MH2 · ch 50 mGL 10.900 · IL 9.000 · depth 1.90 m
MH3 · ch 100 mGL 10.800 · IL 8.800 · depth 2.00 m
MH4 · ch 150 mGL 10.700 · IL 8.600 · depth 2.10 m
MH5 · ch 200 mGL 10.600 · IL 8.400 · depth 2.20 m

Straight line at one gradient and an even ground fall. Real ground levels come from the survey; backdrops, drops across manholes, pipe size changes and minimum self-cleansing velocity (Sewer Flow & Pipe Check) need checking along the actual profile.

What to verify before design ↓

Verify before using in design

  • Ground levels at each manhole from the survey, not an assumed fall.
  • Minimum velocity and capacity with Sewer Flow & Pipe Check; connections and existing services at each manhole.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Nov 2026✓ Tested against worked examples✓ Reviewed by a senior engineer · Nov 2026

Formula

IL = IL₁ − chainage × gradient GL = GL₁ − chainage × ground fall Depth = GL − IL Cover = depth − pipe OD

Standards and references

  • Sewerage authority design manual (cover, depth, manhole spacing)
  • EN 752 (drain and sewer systems outside buildings)
  • Topographic survey

Assumptions

  • Straight line at one gradient; ground falling evenly in the flow direction; no drops at manholes.

Inputs and units

Number of manholes2–30
Distance between manholesm10–120
Pipe gradient%0.1–5
Invert level at the first manholem-50–500
Ground (cover) level at the first manholem-50–500
Ground fall in the flow direction%0–5
Pipe outside diametermm100–2000
Minimum cover over the pipe crownm0.6–2
Maximum manhole depth without special designm3–10

Typical range: last column

Worked example (default values)

  • Number of manholes5
  • Distance between manholes50 m
  • Pipe gradient0.4 %
  • Invert level at the first manhole9.2 m
  • Ground (cover) level at the first manhole11 m
  • Ground fall in the flow direction0.2 %
  • Pipe outside diameter300 mm
  • Minimum cover over the pipe crown1.2 m
  • Maximum manhole depth without special design6 m
Deepest manhole2.20 mCover and depth within the limits entered