Temporary Electrical Supplies on Site
Construction sites are one of the harshest places for electrical equipment: dust, heat, water, vehicles and constant change. Temporary supplies need the same discipline as permanent ones, and often more.
Design and equipment
- Follow IEC 60364-7-704 (construction sites) and the local authority's rules; BS 7375 is a useful code of practice.
- Generators with correct earthing (earth electrode and bonding of the frame), fuel and exhaust safety, and an emergency stop.
- Site distribution boards with suitable IP rating, lockable doors and 30 mA RCDs on socket outlets and hand-held tools.
- Industrial plugs and sockets (IEC 60309); cables suitable for site use (e.g. rubber-sheathed or armoured), routed overhead or protected.
Inspection and testing
- Initial verification before first use, then periodic inspection at short intervals (often every 3 months), recorded.
- Daily user checks of leads and tools; RCD test buttons pressed regularly.
- Portable tools inspected and tagged; damaged items removed immediately.
- Only competent electricians alter the temporary installation.
Gulf site issues
- Heat derates cables and generators: size for high ambient temperature.
- Sun and dust damage plastic enclosures and sockets; use UV-resistant, sealed equipment.
- Welfare cabins and site offices often run on long cable runs: check voltage drop and earth fault loop impedance.
- Keep generators away from excavations, fuel stores and site traffic routes.