Temporary Electrical Supplies on Site

Construction sites are one of the harshest places for electrical equipment: dust, heat, water, vehicles and constant change. Temporary supplies need the same discipline as permanent ones, and often more.

Design and equipment

  • Follow IEC 60364-7-704 (construction sites) and the local authority's rules; BS 7375 is a useful code of practice.
  • Generators with correct earthing (earth electrode and bonding of the frame), fuel and exhaust safety, and an emergency stop.
  • Site distribution boards with suitable IP rating, lockable doors and 30 mA RCDs on socket outlets and hand-held tools.
  • Industrial plugs and sockets (IEC 60309); cables suitable for site use (e.g. rubber-sheathed or armoured), routed overhead or protected.

Inspection and testing

  • Initial verification before first use, then periodic inspection at short intervals (often every 3 months), recorded.
  • Daily user checks of leads and tools; RCD test buttons pressed regularly.
  • Portable tools inspected and tagged; damaged items removed immediately.
  • Only competent electricians alter the temporary installation.

Gulf site issues

  • Heat derates cables and generators: size for high ambient temperature.
  • Sun and dust damage plastic enclosures and sockets; use UV-resistant, sealed equipment.
  • Welfare cabins and site offices often run on long cable runs: check voltage drop and earth fault loop impedance.
  • Keep generators away from excavations, fuel stores and site traffic routes.
Good to knowTest the RCDs on the site boards every week. A tripped RCD is a nuisance; a disabled one is how people die.