Slings, Shackles & Rigging
The crane may be right and the plan approved, but a lift is only as strong as its weakest shackle or sling. Rigging fails through overload at steep angles, damage at sharp edges and lack of inspection.
Ratings and angles
- Every item is marked with its working load limit (WLL) and an identification number linked to its certificate.
- The flatter the sling, the higher the tension: at 30° from horizontal each leg carries the full load. Keep legs at 45° or steeper where possible.
- Choke hitches reduce the sling's capacity (often to about 80 %); basket hitches depend on the angle.
- With three or four legs, assume only two carry the load unless the rigging equalises.
Using rigging
- Protect slings at sharp edges with corner pads or sleeves.
- Load shackles in line with the pin; never side-load beyond the maker's rating.
- Use tag lines to control the load; hands off the load once it is lifted.
- Never lift on a knotted sling, a hand-spliced field repair or an unmarked item.
Inspection
- Inspect before every use: cuts, broken wires, kinks, heat damage, distorted hooks, missing latches.
- Periodic thorough examination by a competent person, often every 6 months (more often for personnel lifting), with a register.
- Many Gulf projects use a coloured tag or tape system to show the current inspection period.
- Damaged items go to quarantine and are destroyed, not returned to the store.
Sling angle factor (one leg, 2-leg sling)
| Angle from horizontal | Tension per leg (load W) |
|---|---|
| 90° (vertical) | 0.50 W |
| 60° | 0.58 W |
| 45° | 0.71 W |
| 30° | 1.00 W |