Lift Planning & Crane Selection
A safe lift is decided at the desk: the right crane, the right configuration, sound ground and a plan everyone understands. On the day, the team only has to follow it.
Choosing the crane
- Start from the heaviest lift and the longest radius, not the average one. Add rigging and the hook block to the load.
- Read the load chart for the exact boom length, radius, counterweight and outrigger setting; capacity falls fast with radius.
- Check access, set-up space, overhead lines and slew clearance before booking.
- Mobile, crawler and tower cranes each suit different jobs: duration, number of lifts and space decide.
Lift categories and plans
- Every lift needs a plan proportionate to its risk. Many projects define routine, complex and critical lifts.
- Lifts above a set share of capacity (often 75–90 %), tandem lifts, lifts over live plant or people, and personnel lifts are usually critical and need an approved detailed plan.
- The plan states the load, rigging, crane configuration, radius, ground pressures, exclusion zone, wind limit and sequence.
People and certificates
- An appointed person or lifting supervisor plans; a crane supervisor controls the lift; a trained slinger/signaller rigs and signals.
- Operators hold the licence or card the authority requires (third-party certification is common in the Gulf).
- Crane and every accessory carry valid third-party inspection certificates; check dates before the lift.
- Wind speed is read at boom height against the maker's limits; Gulf afternoons and shamal winds can change quickly.