Lift Planning & Crane Selection

A safe lift is decided at the desk: the right crane, the right configuration, sound ground and a plan everyone understands. On the day, the team only has to follow it.

Choosing the crane

  • Start from the heaviest lift and the longest radius, not the average one. Add rigging and the hook block to the load.
  • Read the load chart for the exact boom length, radius, counterweight and outrigger setting; capacity falls fast with radius.
  • Check access, set-up space, overhead lines and slew clearance before booking.
  • Mobile, crawler and tower cranes each suit different jobs: duration, number of lifts and space decide.

Lift categories and plans

  • Every lift needs a plan proportionate to its risk. Many projects define routine, complex and critical lifts.
  • Lifts above a set share of capacity (often 75–90 %), tandem lifts, lifts over live plant or people, and personnel lifts are usually critical and need an approved detailed plan.
  • The plan states the load, rigging, crane configuration, radius, ground pressures, exclusion zone, wind limit and sequence.

People and certificates

  • An appointed person or lifting supervisor plans; a crane supervisor controls the lift; a trained slinger/signaller rigs and signals.
  • Operators hold the licence or card the authority requires (third-party certification is common in the Gulf).
  • Crane and every accessory carry valid third-party inspection certificates; check dates before the lift.
  • Wind speed is read at boom height against the maker's limits; Gulf afternoons and shamal winds can change quickly.
Good to knowAsk for the outrigger loads, not just the hook load. Most crane incidents on Gulf sites start with ground that couldn't carry an outrigger.