Crane Lift Utilisation

Total hook load vs chart capacity, and lift category

Design data
t
t
t
t
Settings & basis
ResultPreliminary · verify before design
Utilisation74 %9.20 t total hook load ÷ 12.5 t chart capacity
Within limitRoutine lift by this rule (≤ 75 %); a lift plan is still required
Total hook load9.20 t
Spare capacity3.30 t
Load share of total92 %

Read the capacity from the crane's own load chart for the actual radius, boom length, counterweight and outrigger setting. Some charts already deduct the hook block: check the chart notes. The critical-lift threshold is set by your company or project rules.

What to verify before design ↓

Verify before using in design

  • Lift plan by a competent person; critical lifts approved under the project's lifting procedure.
  • Check wind limits, ground bearing and third-party certificates for crane and accessories.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Oct 2026✓ Tested against worked examples

Formula

Utilisation = (load + rigging + hook block) ÷ chart capacity

Standards and references

  • BS 7121-1 (code of practice for safe use of cranes)
  • ASME B30.5 (mobile and locomotive cranes)
  • EN 13000 (mobile cranes)
  • LOLER 1998 (UK) / local lifting regulations

Assumptions

  • Capacity read from the crane's load chart for the actual radius, boom and outrigger configuration.
  • Total hook load includes all rigging and, unless the chart already deducts it, the hook block.

Inputs and units

Load weightt
Slings, shackles and spreadert
Hook block (if not in the chart)t
Chart capacity at the radius and configurationt0.5–1200
Critical-lift threshold—

Typical range: last column

Worked example (default values)

  • Load weight8.5 t
  • Slings, shackles and spreader0.4 t
  • Hook block (if not in the chart)0.3 t
  • Chart capacity at the radius and configuration12.5 t
  • Critical-lift threshold75 % of capacity
Utilisation74 %Routine lift by this rule (≤ 75 %); a lift plan is still required

Next steps

Found an error? Tell us

Describe the problem briefly (the wrong value, the right one, and the reference if you have it). The page name is sent automatically.