Sling Leg Tension

Load in each sling leg from the sling angle

Design data
t
°
Settings & basis
ResultPreliminary · verify before design
Tension in each loaded leg3.46 t2 legs share the load at 60° from horizontal
Within limitAngle ≥ 45°: each leg needs a WLL of at least 3.46 t
Angle factor (1 ÷ sin θ)1.15
Legs assumed to carry the load2
Angle between legs at the hook (2 legs)60°

Three- and four-leg slings rarely share the load equally, so common practice is to assume only two legs carry it unless the rigging equalises. Use slings and shackles marked with a WLL at least equal to the leg tension, and follow the sling maker's rating for the actual angle and hitch.

What to verify before design ↓

Verify before using in design

  • Use the sling maker's WLL table for the actual angle and hitch (choke, basket).
  • Check the centre of gravity: an off-centre load overloads the shorter leg.
  • Check the edition of each standard that your project specification calls for.
  • Confirm with manufacturer data and the approved design before construction.
Basis & methodVersion 1.0 · Nov 2026Basis last checked: Oct 2026✓ Tested against worked examples

Formula

T = W ÷ (n × sin θ) θ measured from horizontal

Standards and references

  • ASME B30.9 (slings)
  • ASME B30.26 (rigging hardware)
  • BS EN 13414 / EN 1492 (wire rope and textile slings)
  • LEEA Code of Practice

Assumptions

  • Equal leg lengths and a load centred under the hook.
  • Three- and four-leg slings assumed to load only two legs unless equalising rigging is used.

Inputs and units

Load (incl. lifting beam)t
Sling legs—
Angle of each leg from horizontal°30–90

Typical range: last column

Worked example (default values)

  • Load (incl. lifting beam)6 t
  • Sling legs2 legs
  • Angle of each leg from horizontal60 °
Tension in each loaded leg3.46 tAngle ≥ 45°: each leg needs a WLL of at least 3.46 t