Process piping carries hydrocarbons, chemicals, steam and utilities at pressures and temperatures where a leak is a fire or an injury. The code and the piping class decide almost every detail before a pipe is cut.

Codes and piping classes

  • ASME B31.3 covers process piping in plants and terminals; B31.1 covers power piping, and B31.4 / B31.8 cover pipelines.
  • The piping class (spec) fixes the material, pressure rating, corrosion allowance, wall thickness by size, valves, gaskets and bolting.
  • Wall thickness is checked for pressure with allowances (see the calculator), then rounded up to a schedule from ASME B36.10M or B36.19M.

Flanges and ratings

  • ASME B16.5 flanges come in Classes 150 to 2500. The pressure each class allows falls as temperature rises.
  • Mixing classes at a spec break is normal; the lower rating then sets the design limit of that part.
  • Gaskets (spiral-wound, ring-type joint) and bolting must match the class and the service.
  • Bolt tightening for critical joints follows a controlled method (ASME PCC-1) with recorded torques.

Supports, stress and fabrication

  • Hot, large or vibrating lines get a stress analysis (e.g. CAESAR II) to set supports, anchors and expansion loops.
  • Welding follows qualified procedures (WPS / PQR) by qualified welders, with NDT at the percentage the class requires.
  • Some materials and thicknesses need post-weld heat treatment (PWHT) and hardness checks.
  • Material traceability (heat numbers to mill certificates) is checked at receiving and kept in the records.

ASME B16.5 flange ratings, Group 1.1 (e.g. A105) at −29 to 38 °C

ClassMax. pressure (approx.)
15019.6 bar
30051.1 bar
600102.1 bar
900153.2 bar
1500255.3 bar
2500425.5 bar
Good to knowLearn to read the piping class sheet. Half of the site queries on a process job are answered by it.