Pressure Testing & Mechanical Completion

Mechanical completion is the point where construction hands a system to commissioning. On process projects it runs system by system, and the test pack is the paperwork that proves each piping system is ready.

Test packs

  • A test pack groups the lines tested together: marked-up P&ID, isometrics, line list extract and the test limits.
  • Before the test: all welds done, NDT and PWHT cleared, supports in place and the punch list reviewed.
  • Instruments, control valves and relief valves that can't take the test pressure are removed or isolated, and blinds are logged.

Testing

  • Water (hydrostatic) is the default; pneumatic tests need extra approval because of the stored energy.
  • Calibrated gauges at the high and low points, and a relief valve on the test manifold.
  • Vent at the high points, drain at the low points; control the water quality (chloride limits for stainless steel).
  • After the test: drain, dry if needed, remove blinds, reinstate and record each joint.

Mechanical completion and handover

  • The MC certificate is signed per system when it is built, tested and documented to design.
  • Punch list: category A items must be closed before MC; category B items can follow.
  • Pre-commissioning follows: flushing, blowing, drying, leak tests, loop checks and motor solo runs.
  • Then ready for commissioning (RFC), commissioning with process fluids, and start-up.
Good to knowAgree the test-pack format and the punch-list categories with the client at the start. Changing them in the last month delays every system.