Preparing a Method Statement That Gets Approved

A method statement explains how one activity will be done safely and to specification on this project. The consultant approves it before the work starts, and the site team must follow it, so write it for the people who will use it.

Usual sections

  • Purpose and scope; references (specification sections, drawings and revisions, approved materials).
  • Responsibilities: who supervises, who inspects, who signs off.
  • Resources: manpower, plant and tools, test equipment with calibration.
  • Sequence of work, step by step, with the hold and witness points from the ITP.
  • Health and safety: risk assessment, permits, PPE, emergency arrangements.
  • Quality: inspection and test plan, acceptance criteria, forms and records.
  • Environment: dust, noise, waste, spills.

Who does what

  • Site or discipline engineer writes it with the foreman; QA/QC and HSE review; the project or construction manager signs.
  • For subcontracted work, the subcontractor writes it and you review it before it goes to the consultant: you stay responsible.

Why method statements come back with code C

  • Generic text copied from another project or another trade.
  • No link to approved materials or the latest drawings.
  • Missing risk assessment or ITP, or ones that do not match the steps.
  • Test methods and acceptance values not stated.
  • Unclear sequence or missing interfaces with other trades.
Good to knowWalk the sequence on site with the foreman before you submit. If he cannot follow it, the inspector will not accept it.