Risk Assessment, JSA & Method Statements

Every task on site should be thought through before it starts: what can go wrong, how likely, how bad, and what will stop it. The method statement says how the work is done; the risk assessment or JSA says how it is done safely.

RAMS

  • RAMS = risk assessment and method statement, usually submitted to the consultant or client for approval before the activity starts.
  • The method statement covers sequence, resources, equipment, inspections, permits and emergency arrangements.
  • A job safety analysis (JSA) breaks one task into steps and assesses the hazards of each step; it is the version the crew is briefed on.

Scoring risk

  • A common method: risk = likelihood × severity, each scored 1 to 5 on a 5 × 5 matrix.
  • Score the risk before controls, choose controls, then score the residual risk. High residual risk means more controls or a different method.
  • Use the client's or company's matrix where one exists; the bands differ between companies.

Choosing controls

  • Follow the hierarchy of controls: elimination, substitution, engineering, administrative, then PPE as the last line.
  • Prefer controls that don't depend on people remembering: guardrails over harnesses, prefabrication over work at height.
  • Review the RAMS and JSA when the task, crew, equipment or conditions change, and after any incident.

Example risk bands (5 × 5 matrix)

Score (L × S)BandTypical response
1–4LowProceed with normal controls
5–9MediumProceed with specific controls, supervised
10–16HighReduce before work starts; senior approval
20–25Very highDo not start; change the method
Good to knowA JSA that the crew hasn't heard is just paper. Brief it at the work location, in their language, and ask one of them to explain it back.