Responding to Consultant Comments and Resubmitting

Every resubmission costs time on the programme. A clear response to each comment, with the changes easy to find, is the fastest way to approval.

Comment Response Sheet

  • Number every comment and answer each one: revised (where), clarified (how), or not changed (technical reason).
  • Cloud the changes and update the revision; list any other change you made.
  • Do not leave a comment unanswered: it comes back as the same rejection.

Each approval code

  • A, approved: proceed.
  • B, approved as noted: proceed and include the comments; resubmit for record if asked.
  • C, revise and resubmit: do not proceed on that item; answer every comment.
  • D, rejected: new proposal needed; ask why before you start again.

When comments go beyond the contract

  • A comment asking for more than the specification is a possible change: tell the contracts team and answer in writing, reserving your rights.
  • Repeated rejections without clear reasons: request a meeting, minute it and record the delay.
Good to knowPhone the reviewer before you resubmit a code C. Ten minutes of talk often saves a second rejection.

Use with this guide

Free

Comment Response Sheet (CRS)

Every reviewer comment with your response, action, revision and status, with counts of open and disputed comments and a ready-to-resubmit check

  • How to use
  • CRS
  • CRS (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 21 Nov 2026 · blank template with a filled sample · check it against your project specification