Responding to Consultant Comments and Resubmitting
Every resubmission costs time on the programme. A clear response to each comment, with the changes easy to find, is the fastest way to approval.
Comment Response Sheet
- Number every comment and answer each one: revised (where), clarified (how), or not changed (technical reason).
- Cloud the changes and update the revision; list any other change you made.
- Do not leave a comment unanswered: it comes back as the same rejection.
Each approval code
- A, approved: proceed.
- B, approved as noted: proceed and include the comments; resubmit for record if asked.
- C, revise and resubmit: do not proceed on that item; answer every comment.
- D, rejected: new proposal needed; ask why before you start again.
When comments go beyond the contract
- A comment asking for more than the specification is a possible change: tell the contracts team and answer in writing, reserving your rights.
- Repeated rejections without clear reasons: request a meeting, minute it and record the delay.