Project management

Site Instruction, Variation, Method Statement, Work Instruction: the Difference

'Instruction' is used in two worlds on site: the contract (instructions from the engineer that can change cost and time) and the quality system (documents that tell people how to do a task). Mixing them up causes lost claims and failed inspections.

Contract side

  • Site / Engineer's Instruction (SI): a written instruction from the engineer or consultant to do something or do it a certain way.
  • An SI is not automatically a variation: if it asks for work already in the contract, a correction, or a clarification, there is no extra payment.
  • If it changes the work, it is the basis of a Variation Order (VO), which records the change and its value and time.
  • Verbal instruction: confirm it in writing within the contract period (Confirmation of Verbal Instruction).

Quality side (ISO 9001 style)

  • Procedure: who does what and when (company level).
  • Method Statement: how a whole activity is done on this project, with sequence, plant, safety and inspection points.
  • Work Instruction (WI): step-by-step for one task (for example terminating an MV cable or an insulation resistance test), usually company-wide and written for the technician.
  • Forms and records: the proof it was done (checklists, test sheets, inspection requests).

How to tell which one is meant

  • From the consultant, in a letter or SI form: the contract meaning, which can affect cost and time; log it in the Site Instruction Register.
  • In the quality plan or from QA/QC: the quality-system meaning.
Good to knowGive every site instruction a number on the day it arrives, even if it seems minor. Small instructions add up to large variations.

Use with this guide

Free

Site Instruction Register

Every instruction with date, source, written or verbal, confirmation sent, variation yes / no / to check, notice due and sent, and VO reference

  • How to use
  • Register
  • Register (SAMPLE)

Excel (.xlsx) · version 1.0 · revised 21 Nov 2026 · blank template with a filled sample · check it against your project specification

TemplateConfirmation of Verbal InstructionChecklistIs It a Variation?TopicVariation Orders: When You Are Entitled, and Optional Items