Site Instruction, Variation, Method Statement, Work Instruction: the Difference
'Instruction' is used in two worlds on site: the contract (instructions from the engineer that can change cost and time) and the quality system (documents that tell people how to do a task). Mixing them up causes lost claims and failed inspections.
Contract side
- Site / Engineer's Instruction (SI): a written instruction from the engineer or consultant to do something or do it a certain way.
- An SI is not automatically a variation: if it asks for work already in the contract, a correction, or a clarification, there is no extra payment.
- If it changes the work, it is the basis of a Variation Order (VO), which records the change and its value and time.
- Verbal instruction: confirm it in writing within the contract period (Confirmation of Verbal Instruction).
Quality side (ISO 9001 style)
- Procedure: who does what and when (company level).
- Method Statement: how a whole activity is done on this project, with sequence, plant, safety and inspection points.
- Work Instruction (WI): step-by-step for one task (for example terminating an MV cable or an insulation resistance test), usually company-wide and written for the technician.
- Forms and records: the proof it was done (checklists, test sheets, inspection requests).
How to tell which one is meant
- From the consultant, in a letter or SI form: the contract meaning, which can affect cost and time; log it in the Site Instruction Register.
- In the quality plan or from QA/QC: the quality-system meaning.
Use with this guide
Site Instruction Register
Every instruction with date, source, written or verbal, confirmation sent, variation yes / no / to check, notice due and sent, and VO reference